NCERT Solution Class IX Science Work and Energy Question 16 (Ex 11.5)

Question 16:

An object of mass, m is moving with a constant velocity, v. How much work should be done on the object in order to bring the object to rest?

Answer:

Kinetic energy of an object of mass, m moving with a velocity, v is given by the expression,

To bring the object to rest, 1/2 mv2  amount of work is required to be done on the object.