Answer All Questions: (10×2=20 Marks)
- What is Project Management?
- Distinguish between PERT and CPM.
- Explain Internal rate of Return.
- Why is Project Rating Carried out?
- Why is a feasibility study carried out?
- What do you understand by Project Financing?
- What do you understand by Risk analysis?
- What are Project Contracts?
- What are the three types of Costs involved in a Project?
- What is Net Work Analysis?
PART – B
Answer Any FIVE Questions: (5 x 8 = 40Marks)
- What are the Causes of Project Failure?
- Discuss the sources of the positive NPV Project.
- What are the main reasons for SCBA Discrepancies?
- What are the Factors affecting Quality of Estimates?
- What are the Responsibilities of Project Manager?
- What are the Sources of long term Project Finance?
- How Does Network Analysis help in Project Management?
- Explain the internal and external constraints in Project identification.
PART – C
Answer Any TWO Questions: (2 x 20 = 40Marks)
- What are the main contents of Feasibility report?
- Explain the Project life cycle.
- What are the Problems of selecting and managing Project teams?