LOYOLA COLLEGE (AUTONOMOUS), CHENNAI – 600 034
B.A. DEGREE EXAMINATION – ECONOMICS
|
THIRD SEMESTER – April 2009
ST 3103 / 3100 – RESOURCE MANAGEMENT TECHNIQUES
Date & Time: 17/04/2009 / 1:00 – 4:00 Dept. No. Max. : 100 Marks
SECTION- A
Answer all the questions. 10 x 2 = 20 marks
- Write any two applications of operations research.
- Define basic solution for a linear programming problem.
- Distinguish between slack and surplus variables.
- Express a transportation problem as a linear programming problem.
- Why is assignment problem viewed as a particular case of transportation problem?
- What is a sequencing problem?
7 . Provide any two differences between PERT and CPM.
- When is an activity called critical in network analysis?
9 . Write a note on (i) setup cost (ii) holding cost.
10 .State the assumptions of classic EOQ model.
SECTION- B
Answer any five questions 5 x 8 = 40 marks
11.The owner of Metro sports wishes to determine how many advertisements to place in
the selected three monthly magazines A,B and C. His objective is to advertise in such
a way that total exposure to principal buyers of expensive sports good is maximized.
Percentages of readers for each magazine are known. Exposure in any particular
magazine is the number of advertisements placed multiplied by the number of
principal buyers. The following data may be used .
————————————————————————————————————
Magazine
———————————————————————————————————
A B C
Readers 1 lakh 0.6 lakh 0.4 lakh
Principal buyers 20% 15% 8%
Cost per advertisement(Rs.) 8000 6000 5000
————————————————————————————————————
The budgeted amount is at most Rs.1 lakh for the advertisements . The owner has
already decided that magazine A should have no more than 15 advertisements and that
B and C each have at least 80 advertisements. Formulate an LP model for the problem.
- Use the graphical method to solve the following LPP:
Maximize Z = 2x1 + 3x2
Subject to the constraints:
x1 + x2 ≤ 30 , x1 -x2 ≥ 0 , x2 ≥ 3 ,
0≤ x1≤ 20 and 0 ≤ x2 ≤ 12.
- Find all the basic feasible solutions of the equations:
2x1 + 6x2 + 2x3 + x4 = 3
6x1 + 4x2 + 4x3 + 6x4 = 2
- Find an initial basic feasible solution of the following transportation problem using
Vogel’s approximation method:
I II III IV Supply
A 11 13 17 14 250
B 16 18 14 10 300
C 21 24 13 10 400
Demand 200 225 275 250
- Consider the problem of assigning five machines. The assignment costs are given
below :
Machines
Operators A B C D E
I 10 3 10 7 7
II 5 9 7 11 9
III 13 18 2 9 10
IV 15 3 2 12 12
Assign the operators to different machines so that total cost is minimized.
- Determine the optimal sequence of jobs that minimizes the total elapsed time based
on the following information processing time on machines given in hours and
passing is not allowed .
Job : 1 2 3 4 5
Machine A : 3 8 7 5 2
Machine B : 3 4 2 1 5
Machine C : 5 8 10 7 6
Also find the idle time of machines A ,B and C.
- The following table gives the activities in a construction project and time duration :
Activity Preceding activity Normal time (days)
1-2 – 20
1-3 – 25
2-3 1-2 10
2-4 1-2 12
3-4 1-3, 2-3 5
4-5 2-4 , 3-4 10
- Draw the activity network of the project .
- Determine the critical path and the project duration.
- Find the total float and free float for each activity.
- Derive the classic EOQ model clearly stating the assumptions.
SECTION- C
Answer any two questions 2 x 20 = 40 marks
- Use simplex method to
Minimize Z = x1 – 3x2 + 2x3
Subject to
3x1 – x2 + 2x3 ≤ 7
-2x1 – x2 + 2x3 ≤ 12
-4x1 + 3x2 + 8x3 ≤ 10
x1 ≥ 0, x2 ≥ 0, x3 ≥ 0 .
- National oil company (NOC) has three refineries and four depots. Transportation cost
per ton ,capacities and requirements are given below:
________________________________________________________________________
D1 D2 D3 D4 Capacity (tons)
________________________________________________________________________
R1 5 7 13 10 700
R2 8 6 14 13 400
R3 12 10 9 11 800
Requirement (tons) 200 600 700 400
Determine optimum allocation of output.
- A project is composed of eleven activities, the time estimates for which are given
Below:
Activity optimistic time normal time pessimistic time
1-2 7 9 17
1-3 10 20 60
1-4 5 10 15
2-5 50 65 110
2-6 30 40 50
3-6 50 55 90
3-7 1 5 9
4-7 40 48 68
5-8 5 10 15
6-8 20 27 52
7-8 30 40 50
(a) Draw the network diagram for the project.
(b) Calculate total and free floats.
(c) Determine the critical path.
(d) What is the probability of completing the project in 125 days?
- (a) Derive the classic EOQ model with price break.
(b) Neon lights in an industrial park are replaced at the rate of 100 units per day.
The physical plant orders the neon lights periodically. It costs $.100 to initiate a
purchase order, A neon light kept in storage is estimated to cost about $.0.02 per
day. The lead time between placing and receiving an order is 12 days. Determine
the optimum inventory policy for ordering the neon lights.
Latest Govt Job & Exam Updates: