ANSWER ANY TEN QUESTIONS (10×2=20)
- What is a project?
- What is project identification?
- State the objectives of critical path method?
- What do you mean by project description?
- Explain project review?
- State the meaning of WBS?
- What do you mean by cost control?
- What is a project diary?
- What is plant layout?
- Explain SCBA?
SECTION – B
ANSWER ANY FIVE QUESTIONS (5×8=40)
- State the difference between PERT and CPM?
- Explain the role of a project manager in successfully administered project?
- Explain the various steps in project identification?
- Discuss the different stages of cost control methods?
- State the factors affecting factory design?
- Explain the common sources of project finance in developing countries?
- Discuss the various phases of PLC?
- Explain the different components of feasibility study?
SECTION – C
ANSWER ANY TWO QUESTIONS (2×20=40)
- What are the different stages in project formulation?
- Discuss the various components of a project report?
- Explain in detail about the classification of projects?